The minimum list of works on overhaul. The list of works on the overhaul of multi-apartment and multi-storey buildings: what types are included in the list of mandatory buildings and structures

THE GOVERNMENT OF MOSCOW

RESOLUTION

ON ESTABLISHING THE MINIMUM CONTRIBUTION FOR CAPITAL REPAIRS OF COMMON PROPERTY IN APARTMENT BUILDINGS IN THE TERRITORY OF THE CITY OF MOSCOW

In accordance with Article 167 of the Housing Code Russian Federation and Part 2 of Article 7 of the Law of the City of Moscow dated January 27, 2010 N 2 “Fundamentals of the Housing Policy of the City of Moscow” The Moscow Government decides:

  1. Establish that the minimum contribution for the overhaul of common property in apartment buildings in the city of Moscow (hereinafter referred to as the minimum contribution for capital repairs) is calculated in rubles per square meter total area premises in an apartment building based on an assessment of the need for funds to finance services and (or) work on the overhaul of common property in apartment buildings in the city of Moscow, included in the list of services and (or) work on the overhaul of common property in an apartment building on the territory city ​​of Moscow.
  2. Establish the minimum contribution for capital repairs from July 1, 2017 in the amount of 17 rubles per square meter of the total area of ​​residential (non-residential) premises in an apartment building per month. The minimum contribution for capital repairs is subject to annual adjustment to reflect changes in the consumer price index.
  1. Approve the list of works and (or) services for the overhaul of common property in multi-apartment buildings in the city of Moscow, the provision and (or) performance of which is financed from the overhaul funds formed on the basis of the minimum contribution for overhaul (attachment).
  2. Install that:

4.1. The decision to determine the method of forming a capital repair fund must be made and implemented by the owners of premises in an apartment building within 5 months after the official publication of the regional program for the overhaul of common property in apartment buildings in Moscow (hereinafter referred to as the regional program), which includes an apartment building , in respect of which the issue of choosing the method of forming its capital repair fund is being decided.

4.1(1). The obligation to pay contributions for major repairs for the owners of premises in an apartment building put into operation after the approval of the regional program and included in the regional program when it is updated arises after 8 calendar months, starting from the first day of the month following the month of the official publication of the legal act of the Government Moscow, which such an apartment building is included in the regional program.

4.2. Measures of social support for certain categories of citizens for paying for housing apply to the payment of contributions for the overhaul of common property in apartment buildings.

4.2(1). A 50 percent discount on the payment of a contribution for the overhaul of common property in apartment buildings, based on the total area occupied by the residential premises owned by citizens, within the social norm of the area of ​​​​the residential premises, is carried out at the expense of the budget of the city of Moscow and is provided:

– disabled people and families with disabled children;

- persons awarded the medal "For the Defense of Moscow";

- persons residing in Moscow and continuously working at enterprises, organizations and institutions of Moscow, undergoing military service in the city from July 22, 1941 to January 25, 1942;

– Citizens awarded with the badge “Honorary Donor of Russia” or “Honorary Donor of the USSR”;

– citizens awarded with the badge “Honorary Donor of Moscow”;

large families in which three or more children were born and (or) brought up (including adopted children, as well as stepchildren and stepdaughters) until the youngest of them reaches the age of 16, and those studying in educational organizations that implement the main educational programs of primary general education, basic general education, secondary general education - until the age of 18;

- families with 10 or more children under the age of 16, and also over 16 if they are students educational organizations implementing the main educational programs of primary general education, basic general education, secondary general education.

4.2(2). Measures of social support for certain categories of citizens for the payment of a contribution for the overhaul of common property in apartment buildings are provided to citizens for no more than one apartment (dwelling) based on the minimum contribution for overhaul established by this resolution.

4.2(3). In the case when the owner of a dwelling has the right to social support measures for paying a contribution for the overhaul of common property in an apartment building on two or more grounds, these social support measures are provided to him on one of the grounds at the choice of a citizen.

  1. Control over the implementation of this resolution shall be entrusted to the Deputy Mayor of Moscow in the Government of Moscow for housing and communal services and landscaping Biryukov P.P.

Mayor of Moscow

S.S. Sobyanin

Annex to the Decree of the Government of Moscow

SCROLL

WORKS AND (OR) SERVICES ON MAJOR REPAIRS OF COMMON PROPERTY IN APARTMENT BUILDINGS IN THE CITY OF MOSCOW, PROVISION AND (OR) PERFORMANCE OF WHICH ARE FINANCED FROM THE CAPITAL REPAIR FUNDS FORMATED ON THE BASIS OF THE MINIMUM VITAL REPAIR SIZE

  1. Repair of intra-house engineering power supply systems.
  2. Repair of intra-house engineering systems of heat supply.
  3. Repair of intra-house engineering gas supply systems.
  4. Repair of intra-house engineering water supply systems (hot and cold water supply).
  5. Repair of intra-house engineering systems of water disposal (sewerage).
  6. Repair or replacement of elevator equipment recognized as unsuitable for operation, repair of elevator shafts.
  7. Roof repair.
  8. Repair of basements belonging to common property in an apartment building.
  9. Facade repair.

9(1). Replacement of window blocks located in common areas in an apartment building.

  1. Foundation repair.
  2. Repair of the internal smoke exhaust system and fire-fighting automation, repair of the fire water pipeline.
  3. Repair or replacement of a garbage chute located in common areas in an apartment building.
  1. Repair or replacement of internal drainage.
  2. Development and examination of project documentation, including architectural supervision of work on the preservation of cultural heritage objects, identified objects of cultural heritage, scientific supervision of the implementation of these works in the event of work on the overhaul of common property in apartment buildings in the city of Moscow, which are objects cultural heritage, identified objects of cultural heritage, building control, assessing the compliance of elevators with the requirements of the technical regulation of the Customs Union "Safety of elevators" (TR TS 011/2011), approved by the decision of the Commission of the Customs Union of October 18, 2011 N 824 "On the adoption of technical regulation of the Customs Union "Safety of elevators".

The overhaul of common property in apartment buildings is an event prepared in advance in accordance with the work plan, aimed at the qualitative renewal of all communications, carrying out other work and taking measures aimed at improving the quality of life of the owners of premises in a particular building.

The following list of works on major repairs of buildings and structures can be attributed to the activities related to the capital form:

  • restoration of the waterproofing layer on the roof, and in places where this is required by the current state, complete replacement of the roofing;
  • replacement of all necessary communications belonging to common houses;
  • reconstruction of the facade of the building or its replacement (if necessary);
  • the same actions, but performed in relation to the foundation;
  • repair of elevator mechanisms (in cases where these measures are justified from the point of view of the safety of citizens using these mechanisms);
  • replacement of window structures and door blocks;
  • plastering, whitewashing and painting the walls and ceilings of the entrances, as well as all common areas that are classified as common property and included in the estimate for the performance of work.

The same works are given in Appendix No. 8 to the Rules and Norms for the Technical Maintenance of the Housing Stock dated September 27, 2009 No. 170.

This list of works is not exhaustive and can be supplemented if additional items have been agreed with the organization performing the work.

Now that you know what types of work are included in the overhaul of an apartment building, let's talk about the list of services and works for the overhaul of common property in an MKD and what it may have in common with the current one.

What works can be performed both in capital and current repairs?

If we turn to the above articles and analyze the list of works that is presented in the overhaul, comparing it with a similar list from the current one, we can see that there is still a similarity in the work performed.

And what works relate to the overhaul of an apartment building and to the current one?

So, both during the current and during the overhaul, the following activities can be carried out:

  1. Restoration of waterproofing roofing, if necessary.
  2. Insulation of buildings by working on facades (their insulation and painting can be carried out both during current repairs and during major repairs, if required by the operating conditions of the building).
  3. Partial or complete replacement of door blocks and window frames, as well as restoration of lost glazing.
  4. Cosmetic repair of entrances with the elimination of violations of paint and varnish coatings and plaster.

In general, both the scope of work on the overhaul of apartment buildings and for the current one is formed individually for each specific apartment building by making a joint decision between the homeowners and the organization hired to carry them out.

By the way, in the regions there are special programs for major repairs, within the framework of which repairs are carried out on buildings and structures in cities and towns. The sequence of work determines the list of the regional capital repair program, which can be found in local governments.

Influence of operating conditions of an apartment building

The rules and regulations for the operation of the housing stock are considered in a separate section special conditions operation of various buildings intended for human habitation.

Particulars of the operation of buildings located in different territories are entirely devoted to Section No. 6, which discusses the conditions for the use and, accordingly, maintenance of residential premises located on salty soils, in a zone of increased seismic activity, permafrost, etc.

Despite the fact that Appendix No. 8 to these Rules does not fix exactly how operating conditions affect the ongoing repair work, Section 6 contains a direct list of possible violations of the norms for the use of apartment buildings, which must be eliminated during the overhaul.

So, in accordance with Art. 6.2.2, if the building is located on the so-called subsiding soils, that is, there is a very high risk due to the very light and porous structure of the shrinkage of the house, with each repair, all engineering communications must be checked for possible leaks.

With a major overhaul, all communications must be replaced with high-strength materials. Special locking mechanisms should be installed on water supply networks to stop the water supply in the event of a leak (clause B of Art. 6.2.15).

In seismically active zones, during any repair work, partitions should be installed with a wooden frame fixed in the walls of the room (Art. 6.5.5).

After each fact, even minimal seismic activity in accordance with Art. 6.5.10 it is necessary to conduct inspections of the technical condition of buildings with the subsequent drawing up of an inspection report.

It is on the basis of such an act that a decision will be made to carry out current or major repairs. And in the process of performing repair work, it is necessary to strengthen structures that ensure the stability and safety of buildings.

When carrying out repair work in any type of buildings operated in permafrost areas, Special attention should be given to the control, and, if necessary, to the complete repair of the drainage system, as well as sidewalks and slopes of houses in order to prevent water from entering the foundation, as well as freezing of taliks specially designed to ensure the stability of buildings located in the foundations (Art. 6.6.7, 6.6.12).

Capital repairs of water supply and sewerage networks should be carried out not once every 25 years, but with the frequency that will be necessary to prevent the creation of a probable emergency due to emerging leaks.

Thus, the overhaul of any apartment buildings is a rather complicated event, requiring compliance with a number of technical requirements for the work performed.

As for the territories in which the conditions for the operation of the housing stock are especially difficult, there are increased requirements for the work on the overhaul of buildings and their utilities.

We hope that the materials presented in this article are useful for you and you now know what types of work exist during the overhaul of an apartment building, what is the list of works included in the overhaul of an apartment building

On a monthly basis, residents of apartment buildings pay to the regional operator or to the fund of their own house payments for the implementation of capital repairs.

What is included in the list of works on the overhaul of apartment buildings, what will the collected funds be spent on?

What does a major overhaul mean?

Repair work on the common property of an apartment building of a capital nature usually relates to:

  • Reconstruction of walls (except load-bearing).
  • Separate load-bearing structures.
  • Engineering networks and communications.

Properly planned work should gradually repair the failing parts of the common house property and prevent complete wear of the structural elements of the building.

Parts are either repaired or replaced with analogues or latest developments. The work is carried out quite rarely, and this is the reason for the not so large amount of the contribution, which usually accumulates for a long time.

Repair can be:

  • Complex - when the entire building is being renovated, taking into account various innovations that have appeared.
  • Partial - when capital work is envisaged in only one of the directions.

Partial work is good when the amount of damage is not large enough or there are no funds for complex work.

If large amounts of damage or a threat of destruction of a multi-storey building are detected, it is recommended to resettle the residents and conduct an examination - whether further repairs are advisable, or the house is to be demolished.

What works are included in the overhaul of an apartment building

You can find out which houses are included in the program for the overhaul of apartment buildings on the website of the administration of your locality. If no improvement work has been done for a long time:

  • you should check if the house is included in the capital renovation program;
  • check the account on which the funds collected for the overhaul are accumulating, perhaps the funds are simply not enough.

Considering what is usually included in the overhaul of an apartment building, what residents can expect in 2017 and subsequent years, we can highlight:

1. Repair of the walls and facade of the building:

  • Painting and coating with insulation of walls, basement and facades of the building.
  • Replacement of glass and loggias of the house with new or light-saving double-glazed windows.
  • General reconstruction of the external appearance of the building, replacement of facing tiles, barriers and waterproofing.
  • Creation of canopies over the basement, entrance rooms and balconies of the upper floors of the house.
  • Repair of the drainage system.

2. Work with the foundation of an apartment building and basement:

  • Reconstruction of the integrity of the foundation.
  • Restoration of the entrance to the basement.
  • More thorough sealing of the junction of the foundation and engineering networks of the building.

3. Roof and attic repairs:

  • Restoration of all wooden truss and roof structures (if any), their treatment with special compounds against external influences.
  • Tracking and maintenance temperature regime and room humidity.
  • Arrangement of common house TV antennas, lightning rods, etc.

4. Repair work on stairwells and spans:

  • Replacing or updating steps.
  • Repair of stair railings.
  • Painting and plastering work on landings and staircases.

5. Reconstruction of the entrance group to the building and doors:

  • Improvement or restoration of access doors, doors to the vestibule and to the floors, if any.
  • Restoration or renewal of the steps of the entrance group.
  • Update of the stair railing at the entrance to the entrance.

6. Repair of the heating system of an apartment building;

  • Replacement of pipes and risers that are out of order or with an expiring service life.
  • Repair or installation of heat level regulators.
  • Installation of shutoff valves.
  • Technical improvement of the heating system;

7. Repair and cleaning of the ventilation system and shafts from accumulated debris, replacement of gratings.

8. Recovery of hot and cold water;

  • Restoration of worn sections of water pipes.
  • Update of hardware and equipment.
  • Installation and replacement of water meters for hot and cold water.
  • Replacement of plumbing (if any) in common areas.

9. Repair of the power supply system:

  • Maintenance and replacement of floor and common house electricity meters.
  • Replacement of lighting fixtures in common areas.
  • Installation of anti-vandal complexes and energy-saving devices.

10. Disinfection and reconstruction of garbage chutes (if any).

11. Installation of floor-by-floor fire-fighting complexes and alarm systems.

12. Reconstruction of the uninterrupted operation of the gas supply system, transfer of gas pipe locations, replacement and installation of new equipment.

13. Partial repair or complete replacement of elevators and elevator shafts, providing access to elevators for people with limited mobility.

An important feature of the overhaul is that it is aimed at improving or replacing property that belongs to all residents of an apartment building on the basis of common ownership. The money collected from receipts cannot be spent on cosmetic repairs and decoration of private apartments. The only case when this happens is the restoration of the finish in the apartment if it is damaged during replacement when replacing plumbing and pipes.

How is a repair decision made?

In order to conclude that some important elements of the house need major repairs, it is necessary to convene a commission that analyzes the performance of all elements and systems of an apartment building and identifies negative factors that worsen the condition of these elements.

At the same time, an assessment of all elements and structures should be carried out in accordance with the technical passport of the house, the percentage of their wear and tear is indicated.

The general meeting of residents must make a written decision on the need for a major overhaul based on the assessments and expertise received. The meeting decides how such repairs will be financed and what works are included in the overhaul of the apartment building to improve its current condition.

An example of self-organization of tenants in the video:

The overhaul is aimed not only at restoring the performance of existing systems, but also improving them with high-tech materials and new products and increasing the life of the building.

Repair work, as a rule, depending on the frequency of carrying out, is divided into two types: current repair and overhaul.

List of works on overhaul

Lists of types of work on capital repairs are contained in departmental acts (Regulations, Norms and Rules .., Instructions, Recommendations, etc. ..). These lists of types of work vary depending on the type of object. capital construction, his destination.

Types of work are given in annexes to departmental regulations, the texts of which are given in the attachment to this publication:

Appendix 8. List of works on major repairs of buildings and structures ( Decree of the Gosstroy of the USSR of December 29, 1973 N 279 "On approval of the Regulations on the scheduled preventive maintenance of industrial buildings and structures" (together with "MDS 13-14.2000 ..."))

Appendix N 8. An approximate list of works performed during the overhaul of the housing stock ( Decree of the Gosstroy of the Russian Federation of September 27, 2003 N 170 "On approval of the Rules and norms for the technical operation of the housing stock")

Appendix 9. List of works on the overhaul of buildings and structures ( Order of the Ministry of Justice of Russia dated September 28, 2001 N 276 (as amended on January 24, 2006) "On approval of the instructions for the technical operation of buildings and structures of institutions of the penitentiary system")

Table 2.3. The list of works on the overhaul of apartment buildings to be included in the scope of works financed from the funds provided for by Federal Law N 185-FZ ( )

Definition of the concept of "overhaul" in the NPA

Overhaul- repairs carried out to restore the technical and economic characteristics of the object to values ​​close to the design ones, with the replacement or restoration of any constituent parts (Order of the Gosstroy of the Russian Federation of December 13, 2000 N 285 "On approval of the Standard Instructions for the Technical Operation of Heat Networks of Public Heat Supply Systems").

Overhaul- carrying out a complex of construction works and organizational and technical measures to eliminate physical and moral deterioration, not related to a change in the main technical and economic indicators of the building and its functional purpose, providing for the restoration of its resource with partial replacement, if necessary, of structural elements and systems of engineering equipment, as well as improvement performance indicators ( Decree of the Government of Moscow of July 30, 2002 N 586-PP (as amended on December 23, 2015) "On approval of the Regulations on the unified procedure for pre-project and design preparation for the construction of utilities, facilities and road transport facilities in the city of Moscow").

Capital repairs of capital construction facilities(with the exception of linear facilities) - replacement and (or) restoration of building structures of capital construction objects or elements of such structures, with the exception of load-bearing building structures, replacement and (or) restoration of engineering and technical support systems and networks of engineering and technical support of capital construction objects or their elements, as well as the replacement of individual elements of load-bearing building structures with similar or other elements that improve the performance of such structures and (or) the restoration of these elements ( (as amended on 06/18/2017)

Capital repairs of buildings and structures

For the overhaul of buildings and structures include works on the restoration or replacement of individual parts of buildings (structures) or entire structures, parts and engineering equipment due to their physical wear and tear and destruction with more durable and economical ones that improve their performance ( Decree of the Gosstroy of Russia dated 03/05/2004 N 15/1 (as amended on 06/16/2014) "On approval and implementation of the Methodology for determining the cost of construction products on the territory of the Russian Federation" (together with "MDS 81-35.2004 ...")).

Building overhaul- a set of construction and organizational and technical measures to eliminate physical and functional (moral) wear and tear that do not involve changes in the main technical and economic indicators of a building or structure, including, if necessary, the replacement of individual or all structural elements (except for non-replaceable) and engineering systems equipment with their modernization. Capital repairs do not extend the service life of buildings, as it is determined by the most durable elements that are not replaced during repairs ( "Methodological recommendations for the formation of the scope of works for the overhaul of apartment buildings financed from the funds provided for by the Federal Law of July 21, 2007 N 185-FZ "On the Fund for Assistance to the Reform of the Housing and Communal Services" (approved by the State Corporation "Fund for Assistance to the Reform of Housing and Communal Services" 15.02.2013)

Capital repairs of an apartment building

Capital repairs of an apartment building- carrying out and (or) rendering of the works and (or) services provided for by this Federal Law to eliminate malfunctions of worn-out structural elements of the common property of owners of premises in an apartment building (hereinafter referred to as common property in an apartment building), including their restoration or replacement, in in order to improve the performance of common property in an apartment building ( article 2 of the Federal Law of July 21, 2007 N 185-FZ (as amended on June 23, 2016) "On the Fund for Assistance to the Reform of Housing and Communal Services").

Capital repairs of the common property of an apartment building: a set of works (services) for the replacement and (or) restoration (repair) of the bearing and (or) functional capacity of structures, parts, engineering and technical support systems, individual elements of the supporting structures of an apartment building that have lost during operation to similar or other improving indicators up to their normative state, when the volume of such work exceeds the current repair ( )

Types of overhaul

Comprehensive and selective overhaul

Overhaul is divided into complex overhaul and selective overhaul.
a) is a repair with the replacement of structural elements and engineering equipment and their modernization. It includes work covering the entire building as a whole or its individual sections, in which their physical and functional wear is compensated.
b) is a repair with full or partial replacement of individual structural elements of buildings and structures or equipment, aimed at full compensation for their physical and partially functional wear.
Attribution to the type of overhaul depends on the technical condition of the buildings assigned for repair, as well as the quality of their planning and the degree of internal improvement ( "Methodological recommendations for the formation of the scope of works for the overhaul of apartment buildings financed from the funds provided for by the Federal Law of July 21, 2007 N 185-FZ "On the Fund for Assistance to the Reform of the Housing and Communal Services" (approved by the State Corporation "Fund for Assistance to the Reform of Housing and Communal Services" 15.02.2013))

Complete overhaul: replacement, restoration and (or) repair of the common property of an apartment building or its individual parts, carried out in relation to the majority of the common property of an apartment building ( "GOST R 51929-2014. National standard of the Russian Federation. Services of housing and communal services and management of apartment buildings. Terms and definitions" (approved and put into effect by Order of Rosstandart dated 11.06.2014 N 543-st)

Complex overhaul- covers all elements of the building, provides for the simultaneous restoration of all worn-out structural elements, engineering equipment and an increase in the degree of improvement of the building as a whole, eliminates physical and moral deterioration. It is not advisable to carry out the next comprehensive overhaul of a building or structure in cases where it is planned to demolish or transfer buildings or structures in connection with the upcoming construction on the site they occupy of another building or structure, the building is to be reconstructed, the building is planned to be dismantled due to general dilapidation. In these cases, work must be carried out to maintain the structures of the building or structure in a condition that ensures their normal operation during the appropriate period (before demolition or reconstruction) ( )

Overhaul selective: replacement (restoration) of the common property of an apartment building or its individual parts, carried out in relation to a smaller part (some parts) of the common property of an apartment building ( "GOST R 51929-2014. National standard of the Russian Federation. Services of housing and communal services and management of apartment buildings. Terms and definitions" (approved and put into effect by Order of Rosstandart dated 11.06.2014 N 543-st)

Selective overhaul- covers individual structural elements of the building or its engineering equipment, while eliminating the physical wear and tear of individual elements and technical systems of the building. Selective overhaul is carried out in cases where a comprehensive overhaul of a building can cause serious interference in the operation of the facility, with significant wear of individual structures that threaten the safety of other parts of the building, if it is not economically feasible to carry out a comprehensive overhaul according to the restrictions given in the definition of a comprehensive overhaul ( Decree of the Government of Moscow dated September 29, 2010 N 849-PP (as amended on July 7, 2015) "On approval of the Regulations for the overhaul of real estate objects owned by the state of the city of Moscow and transferred to trust management")

Emergency overhaul- repair or replacement of all structural elements, devices, systems of engineering equipment that failed due to accidents, natural Disasters, terrorist attacks and vandalism ( Decree of the Government of Moscow dated September 29, 2010 N 849-PP (as amended on July 7, 2015) "On approval of the Regulations for the overhaul of real estate objects owned by the state of the city of Moscow and transferred to trust management")

Capital repairs of external engineering communications

For the overhaul of external engineering communications and improvement facilities include repair of water supply networks, sewerage, heat and gas supply and electricity supply, landscaping of courtyard areas, repair of paths, driveways and sidewalks, etc. ( Decree of the Gosstroy of Russia dated 03/05/2004 N 15/1 (as amended on 06/16/2014) "On approval and implementation of the Methodology for determining the cost of construction products on the territory of the Russian Federation" (together with "MDS 81-35.2004 ...")

Capital repairs of roads

Capital repairs of the highway- a set of works for the replacement and (or) restoration of structural elements of the highway, road structures and (or) their parts, the implementation of which is carried out within the established permissible values ​​and specifications the class and category of the motor road, and the implementation of which affects the design and other characteristics of the reliability and safety of the motor road and does not change the boundaries of the right of way of the motor road ( Art. 3 of the Federal Law of November 8, 2007 N 257-FZ (as amended on February 7, 2017) "On highways and road activities in the Russian Federation and on amendments to certain legislative acts of the Russian Federation")

Capital repairs of the road surface- a set of works in which the complete restoration and improvement of the performance of pavement and pavement, subgrade and road structures is carried out, worn-out structures and parts are replaced or replaced with the most durable and durable, increasing the geometric parameters of the road, taking into account the increase in traffic intensity and axial loads vehicles within the limits corresponding to the category established for the road being repaired, without increasing the width of the subgrade along the main length of the road ( Order of the Ministry of Housing and Public Utilities of the Moscow Region of June 29, 2015 N 125-RV "On Approval of the Rules for the Improvement of the Territory of the Balashikha Urban District of the Moscow Region")

Period of overhaul. Reasonable time

The terms for the overhaul are either established by the parties, or established by regulatory legal acts (NLA). In the absence of an indication of the timing of the repair in the contract or regulation, it is carried out within a reasonable time.

The concept of "reasonable time" is traditional for civil law and is mentioned repeatedly in the norms of the Civil Code of the Russian Federation (see Article 314 of the Civil Code of the Russian Federation, in relation to pledge relations - paragraph 4 of Article 345, paragraph 1 of Article 358 of the Civil Code of the Russian Federation).

A reasonable period for carrying out a major overhaul depends on the condition of the property, its properties, climate features, features of the overhaul, technical capabilities and other reasons.

In addition, the regulatory legal acts can provide for both specific terms for the repair, and the procedure for determining them can be fixed, and the frequency of performing certain types of repair work can be established.

Investments:

; Appendix 8 to the Decree of the USSR Gosstroy of December 29, 1973 N 279 "On approval of the Regulations on the scheduled preventive maintenance of industrial buildings and structures" (together with "MDS 13-14.2000 ...")

Annex 8

SCROLL
WORKS ON CAPITAL REPAIRS OF BUILDINGS AND STRUCTURES

A. BY BUILDINGS

I. Foundations

1. Changing wooden chairs or replacing them with stone or concrete pillars.
2. Partial re-laying (up to 10%), as well as strengthening of stone foundations and basement walls, not associated with the superstructure of the building or additional loads from newly installed equipment.
3. Restoration of vertical and horizontal insulation of foundations.
4. Restoration of the existing blind area around the building (more than 20% of the total blind area).
5. Repair of existing drains around the building.
6. Change of single collapsing stone and concrete pillars.

II. Walls and columns

1. Sealing cracks in brick or stone walls with clearing furrows, with bandaging of seams with old masonry.
2. Installation and repair of structures that reinforce stone walls.
3. Re-laying of dilapidated brick cornices, lintels of pit parapets and protruding parts of walls.
4. Relocation and repair of individual dilapidated sections of stone walls up to 20% of the total volume of masonry, not related to the superstructure of the building or additional loads from newly installed equipment.
5. Strengthening of reinforced concrete and stone columns with clips.
6. Repair and partial replacement (up to 20% of the total volume) of columns that are not associated with additional loads from newly installed equipment.
7. Change of aggregates in walls with stone, reinforced concrete and metal frames (up to 40%).
8. Change of dilapidated crowns of log or block walls (up to 20% of the total surface of the walls).
9. Continuous caulking of log or block walls.
10. Partial replacement of sheathing, backfilling and slab heaters of frame walls (up to 50% of the total wall area).
11. Change or repair of sheathing and insulation of wooden plinths.
12. Repair of stone plinths of wooden walls with their re-laying up to 50% of the total volume.
13. Setting up again and changing worn clamps of log and block walls.

III. Partitions

1. Repair, change and replacement of worn-out partitions with more advanced designs of all types of partitions.
2. During the overhaul of partitions, partial redevelopment is allowed with an increase in the total area of ​​the partitions by no more than 20%.

IV. Roofs and coverings

1. Replacing dilapidated wooden roof trusses or replacing them with prefabricated reinforced concrete.
2. Complete or partial replacement of dilapidated metal and reinforced concrete trusses, as well as replacement of metal trusses with prefabricated reinforced concrete trusses.
3. Reinforcement of trusses when replacing types of coating (replacing wood slabs with precast concrete, cold coating - with warm, etc.), during suspension of lifting devices, as well as during corrosion of nodes and other elements of metal and prefabricated reinforced concrete trusses.
4. Partial or complete change of rafters, mauerlats and battens.
5. Repair of supporting structures of skylights.
6. Repair of devices for opening the covers of skylights.
7. Partial or complete replacement of dilapidated elements of coatings, as well as replacing them with more progressive and durable ones.
8. Partial (over 10% of the total roof area) or complete change or replacement of all types of roofing.
9. Reconstruction of roofs in connection with the replacement of the roofing material.
10. Partial or complete replacement of wall gutters, slopes and covers of chimneys and other protruding devices above the roof.

V. Interfloor ceilings and floors

1. Repair or change of floors.
2. Replacing individual structures or ceilings as a whole with more progressive and durable structures.
3. Strengthening of all types of interfloor and attic floors.
4. Partial (more than 10% of the total floor area in the building) or complete replacement of all types of floors and their bases.
5. Reconstruction of floors during repairs with replacement with stronger and more durable materials. In this case, the type of floors must comply with the requirements of standards and specifications for new construction.

VI. Windows, doors and gates

1. Complete replacement of dilapidated window and door blocks, as well as gates of industrial buildings.

VII. Stairs and porches

1. Partial or complete change of landings, ramps and porches.
2. Change and strengthening of all types of stairs and their individual elements.

VIII. Internal plastering, facing
and painting work

1. Renewal of plastering of all premises and repair of plastering in the amount of more than 10% of the total plastered surface.
2. Change of wall cladding in the amount of more than 10% of the total area of ​​clad surfaces.
3. Continuous anti-corrosion painting of metal structures.

IX. facades

1. Repair and renewal of lining with an area of ​​more than 10% of the lined surface.
2. Full or partial (more than 10%) renewal of the plaster.
3. Complete renewal of rods, cornices, belts, sandriks, etc.
4. Renewal of stucco details.
5. Continuous coloring with stable compositions.
6. Cleaning the facade with sandblasters.
7. Change of balcony slabs and railings.
8. Change of coatings of the protruding parts of the building.

1. Complete refurbishment of all types of heating furnaces, chimneys and their foundations.
2. Re-equipment of furnaces for burning coal and gas in them.
3. Complete refurbishment of kitchen stoves.

XI. Central heating

1. Change of individual sections and assemblies of heating boilers, boilers, boiler units or complete replacement of boiler units (in the event that the boiler unit is not an independent inventory object).
2. Repair and replacement of expanders, steam traps and other network equipment.
3. Repair and re-laying of foundations for boilers.
4. Automation of boiler rooms.
5. Transfer from stove heating to central heating.
6. Change of heating registers.
7. Connection of buildings to heating networks (with a distance from the building to the network of no more than 100 m).

XII. Ventilation

1. Partial or complete change of air ducts.
2. Change fans.
3. Rewinding or changing electric motors.
4. Change of gates, deflectors, throttle valves, blinds.
5. Partial or complete change of ventilation ducts.
6. Change of heaters.
7. Change of heating units.
8. Change filters.
9. Change of cyclones.
10. Change of individual chamber designs.

XIII. Water supply and sewerage

1. Partial or complete change of piping inside the building, including water supply inlets and sewer outlets.

XIV. Hot water supply

1. Change of coils and boilers.
2. Change of the pipeline, parts and, in general, pumping units, tanks and pipeline insulation.

XV. Electrical lighting and communications

1. Change of worn-out sections of the network (more than 10%).
2. Change of safety guards.
3. Repair or restoration of cable channels.
4. During the overhaul of the network, it is allowed to replace lamps with other types (ordinary ones with fluorescent ones).

B. BY FACILITIES

XVI. Water supply and sewerage facilities

a) Pipelines and network fittings

1. Partial or complete replacement of anti-corrosion insulation of the pipeline.
2. Change of individual pipeline sections (due to pipe wear) without changing the pipe diameter. At the same time, it is allowed to replace cast-iron pipes with steel pipes, ceramic pipes with concrete or reinforced concrete pipes and vice versa, but it is not allowed to replace asbestos-cement pipes with metal pipes (except in emergency cases).

3. Change of worn fittings, valves, fire hydrants, air vents, valves, standpipes or their repair with the replacement of worn parts.
4. Change of individual siphon pipes.

b) Wells

1. Repair of cell wells.
2. Change hatches.
3. Stuffing new trays to replace the destroyed ones.
4. Replacement of worn-out wooden wells.
5. Renewal of plaster.

c) Water intakes and hydraulic structures

1. Dams, dams, spillways, canals

1. Change or replacement of fastening of banks or slopes in the amount of up to 50%.
2. Filling up swollen slopes of earthworks.
3. Change of clothes.
4. Renewal of the protective layer in the underwater parts of reinforced concrete structures.
5. Change of lattices and grids.
6. Repair and replacement of shield gates.

2. Water wells

1. Construction and dismantling of an oil rig or installation and dismantling of an inventory drilling rig.
2. Cleaning the well from collapses and siltation.
3. Removing and installing a new filter.
4. Fixing the well with a new column of casing pipes.
5. Replacement of water and air pipes.
6. Restoration of well flow rate by torpedoing or flushing with hydrochloric acid.
7. Cementation of the annular space and drilling of cement.

d) Treatment facilities

1. Repair and replacement of fully waterproofing.
2. Repair and renewal of plaster and ironwork.
3. Relaying brick walls and partitions up to 20% of the total volume of masonry in the building.
4. Sealing leaks in reinforced concrete, concrete and stone walls and bottoms of structures with concrete dismantling in separate places and concrete again.
5. Continuous gunning of the walls of structures.
6. Repair of drainage around structures.
7. Replacement of tank hatches.
8. Replacement of gratings.
9. Replacement of loading filters, biofilters, air filters.
10. Change of filter plates.
11. Replacement of pipelines and fittings.
12. Relaying the drainage system of the silt pads.

XVII. Heat supply

a) Channels and cameras

1. Partial or complete change of coatings of channels and chambers.
2. Partial or complete change of waterproofing of channels and chambers.
3. Partial re-laying of the walls of brick channels and chambers (up to 20% of the total surface of the walls).
4. Partial relocation of drainage systems.
5. Repair of the bottoms of channels and chambers.
6. Renewal of the protective layer in reinforced concrete structures of channels and chambers.
7. Change hatches.

b) Pipelines and fittings

1. Partial or complete change of thermal insulation of the pipeline.
2. Renewal of pipeline waterproofing.
3. Change of individual sections of the pipeline (due to pipe wear) without increasing the diameter of the pipes.
4. Change of fittings, valves, compensators or their repair with the replacement of worn parts.
5. Replacement of movable and fixed supports.

XVIII. Access and internal railway tracks

a) ground bed

1. Broadening of the subgrade in places of insufficient width to normal sizes.
2. Treatment of subgrade in places of landslides, erosion, landslides, abysses.
3. Restoration of all drainage and drainage devices.
4. Restoration of all protective and fortifying structures of the subgrade (sodding, paving, retaining walls).
5. Restoration of regulatory structures.
6. Correction, filling up the cones of bridges.
7. Change of individual structures of artificial structures or their replacement with other structures, as well as a complete change of pipes and small bridges (if they are not independent inventory objects, but are part of the subgrade).

b) The superstructure of the track

1. Cleaning the ballast layer or updating the ballast with bringing the ballast prism to the dimensions established by the standards for of this type way.
2. Change of unusable sleepers.
3. Change of worn rails.
4. Change of unusable fasteners.
5. Straightening curves.
6. Repair of turnouts with the replacement of individual elements and transfer bars.
7. Change of turnouts.
8. Repair of the bridge deck.
9. Change of flooring of crossings or replacement of wood with reinforced concrete.

c) Artificial structures (bridges, tunnels, pipes)

1. Partial replacement of elements or complete replacement of worn-out superstructures.
2. Partial re-laying of stone and brick supports (up to 20% of the total volume).
3. Repair of concrete supports (up to 15% of the total volume).
4. Gunning or grouting of the surface of the supports.
5. Arrangement on supports of reinforcing reinforced concrete shells (jackets).
6. Repair or complete change of insulation.
7. Change of bridge beams.
8. Change of anti-theft bars.
9. Change of wooden flooring.
10. Change of flooring from reinforced concrete slabs.
11. Change of counter rails.
12. Change of damaged elements of wooden bridges, except for piles.
13. Replacement of wooden packages with reinforced concrete superstructures.
14. Partial re-laying of stone and brickwork of vaults and walls of tunnels.
15. Injection of cement mortar behind the tunnel lining.
16. Repair and replacement of drainage devices of tunnels.
17. Relocation of the pipe head.
18. Change of elements of wooden pipes (up to 50% of the volume of wood).
19. Change of elements of reinforced concrete or concrete pipes (up to 50% of the volume).

XIX. Car roads

a) ground bed

1. Treatment of subgrade in places of landslides, landslides, erosion and deeps.
2. Restoration of all drainage and drainage devices.
3. Restoration of all protective and fortifying structures of the subgrade.
4. Change of individual structures of artificial structures or their replacement with other structures, as well as a complete change of pipes and small bridges (if they are not independent inventory objects, but are part of the subgrade or road as a single inventory object).

b) Road clothes

1. Alignment and replacement of individual cement-concrete slabs.
2. Laying a leveling layer of asphalt concrete on the cement-concrete surface.
3. Installation of asphalt concrete pavement on roads with cement-concrete pavement.
4. Change of cement-concrete coating to a new one.
5. Strengthening the asphalt concrete pavement.
6. Reconstruction of crushed stone and gravel coatings.
7. Relocation of pavements.
8. Profiling of dirt roads.

c) Bridges, pipes

1. Partial re-laying of stone and brick supports (up to 20% of the total volume).
2. Repair of concrete supports (up to 15% of the total volume).
3. Change of damaged elements of wooden bridges, except for piles.
4. Change of wooden or reinforced concrete flooring, as well as replacement of wooden flooring with reinforced concrete.
5. Complete change or replacement of superstructures.
6. Relocation of pipe heads.
7. Change of elements of wooden, reinforced concrete or concrete pipes (up to 50% of the volume).

d) Sites for cars, road construction
and other machines, storage areas, as well as areas
grain receiving points

1. Repair and restoration of drainage structures (trays, ditches, etc.).
2. Relocation of cobblestone areas.
3. Reconstruction of crushed stone and gravel surfaces of sites.
4. Repair of concrete pads with laying a leveling layer of concrete.
5. Alignment and replacement of individual cement-concrete slabs.
6. Covering with asphalt concrete the sites listed in paragraphs 2 - 5.

XX. Electrical networks and communications

1. Change or replacement of unusable fittings.
2. Replacing hooks with traverses.
3. Change of wires.
4. Repair and change of end and connecting cable boxes.
5. Repair or replacement of grounding devices.
6. Change of supports (up to 30% per 1 km).
7. Installation of cable wells.

XXI. Other structures

1. Repair, change or replacement with other supports of racks for air laying of pipelines.
2. Repair or change of platforms, stairs and railings for overhead pipelines.
3. Repair or replacement of individual columns (up to 20%) of crane racks.
4. Repair or change of crane beams of crane racks.
5. Repair of galleries and fuel supply racks of boiler and gas generating substations with a change (up to 20%) of structures without changing foundations.
6. Change or complete replacement of wooden fence posts (fences).
7. Repair or replacement of individual concrete and reinforced concrete pillars (up to 20%) and fences (fences).
8. Repair of individual sections of filling between fence posts (up to 40%).
9. Repair of separate sections of solid stone fences (up to 20%).
10. Repair of individual sections of solid adobe fences (up to 40%).
11. Repair of chimneys with the change or replacement of the lining, with the installation of hoops, with the restoration of the protective layer of reinforced concrete pipes.
12. Repair and replacement of individual sections of metal chimneys.
13. Repair of ash and slag dischargers with complete replacement of individual sections of the pipeline (without increasing the diameter).
14. Repair of loading platforms with a complete change of wooden flooring, blind area or asphalt. Change of individual supports or sections of retaining walls (up to 20%). In the event that the unloading area is part of a storage facility (ramp), a complete change or replacement of all structures is allowed.

An approximate list of works performed during the overhaul of the housing stock; Appendix 8 to the Decree of the Gosstroy of the Russian Federation of September 27, 2003 N 170 "On approval of the Rules and norms for the technical operation of the housing stock"

EXAMPLE LIST
WORKS CARRIED OUT DURING MAJOR REPAIRS
HOUSING FUND

1. Inspection of residential buildings (including a complete survey of the housing stock) and preparation of design estimates (regardless of the period of repair work).
2. Repair and construction work to change, restore or replace elements of residential buildings (except for the complete replacement of stone and concrete foundations, load-bearing walls and frames).
3. Modernization of residential buildings during their overhaul (re-planning, taking into account the downsizing of multi-room apartments; installation of additional kitchens and sanitary facilities, expansion of living space due to auxiliary premises, improvement of insolation of residential premises, elimination of dark kitchens and entrances to apartments through kitchens with a device, with necessary, built-in or attached premises for stairwells, sanitary facilities or kitchens); replacement of furnace heating with central heating with the installation of boiler rooms, heat pipelines and heat points; roof and other autonomous sources of heat supply; re-equipment of furnaces for burning gas or coal in them; equipment with cold and hot water supply, sewerage, gas supply systems with connection to existing main networks with a distance from the input to the point of connection to the mains up to 150 m, the installation of gas ducts, water pumps, boiler rooms; complete replacement of existing central heating systems, hot and cold water supply (including with the obligatory use of modernized heating devices and pipelines made of plastic, metal-plastic, etc. and a ban on the installation of steel pipes); installation of household electric stoves instead of gas stoves or kitchen hearths; installation of elevators, garbage chutes, pneumatic waste disposal systems in houses with a landing of the upper floor of 15 m and above; transfer of the existing power supply network to increased voltage; repair of television antennas for collective use, connection to the telephone and radio broadcasting networks; installation of intercoms, electric locks, installation of fire-fighting automation and smoke removal systems; automation and dispatching of elevators, heating boilers, heating networks, engineering equipment; landscaping of courtyard areas (paving, asphalting, landscaping, fencing, wood sheds, equipment for children's and household playgrounds). Repair of roofs, facades, joints of prefabricated buildings up to 50%.
4. Insulation of residential buildings (works to improve the heat-shielding properties of enclosing structures, the installation of window fillings with triple glazing, the installation of external vestibules).
5. Replacement of intra-quarter engineering networks.
6. Installation of metering devices for the consumption of thermal energy for heating and hot water supply, the consumption of cold and hot water for the building, as well as the installation of apartment meters for hot and cold water (when replacing networks).
7. Reconstruction of non-ventilated combined roofs.
8. Author's supervision of design organizations for the overhaul of residential buildings with full or partial replacement of ceilings and redevelopment.
9. Technical supervision in cases where subdivisions for technical supervision of major repairs of the housing stock have been created in local governments and organizations.
10. Repair of built-in premises in buildings.

List of works on major repairs of buildings and structures; Appendix 9 to the Order of the Ministry of Justice of Russia dated September 28, 2001 N 276 (as amended on January 24, 2006) "On approval of the instructions for the technical operation of buildings and structures of institutions of the penitentiary system")

Appendix 9

LIST OF WORKS FOR CAPITAL REPAIRS OF BUILDINGS AND STRUCTURES

1.1. Foundations.
1.1.1. Changing wooden chairs or replacing them with stone or concrete pillars.
1.1.2. Partial re-laying (up to 15%), as well as strengthening of foundations and basement walls under the outer and inner walls and pillars of stone and wooden buildings that are not connected with the building superstructure or with additional loads from newly installed equipment.
1.1.3. Strengthening the foundations for the foundations of stone buildings that are not related to the superstructure of the building.
1.1.4. Restoration of vertical and horizontal insulation of foundations.
1.1.5. Restoration of the settled existing or construction of a new blind area around the building (more than 20% of the total blind area) in order to protect the soil under the foundations from erosion or waterlogging.
1.1.6. Repair of brick cladding of foundation walls from the basement side in separate places with the laying of more than 10 bricks in one place.
1.1.7. Partial or complete restoration or installation of new waterproofing in the basement.
1.1.8. Partial or complete re-laying of pits at the windows of the basement and basement floors.
1.1.9. Replacing rotten wooden foundation chairs in wooden buildings with new wooden, brick, concrete or reinforced concrete pillars.
1.1.10. Repair of existing drains around the building.
1.1.11. Replacement of single collapsing stone and concrete pillars.
Note. At the expense of funds for major repairs, it is possible to artificially fix the soils of foundations by chemical, thermal and other methods.

1.2. Walls and columns.
1.2.1. Relaying brick plinths (more than 10 bricks in one place).
1.2.2. Sealing of cracks in brick or stone walls with furrow clearing, with dressing of seams with old masonry.
1.2.3. Arrangement and repair of structures reinforcing stone walls.
1.2.4. Relaying dilapidated brick cornices, lintels, parapets, pits and protruding parts of walls.
1.2.5. Full or partial re-laying and fastening of individual dilapidated sections of brick walls (up to 25% of their total area in the building) that are not associated with the superstructure of the building or with additional loads from newly installed equipment, as well as the change of individual crowns in wooden buildings, also not exceeding 25% common wall surface.
1.2.6. Reinforcement of walls with tension and metal ties.
1.2.7. Change of fillings in walls with stone, reinforced concrete and metal frames (up to 40%).
1.2.8. Sealing cracks in brick walls with excavation and clearing of old masonry and installation of a new one, with bandaging of seams with old masonry.
1.2.9. Restoration of the waterproofing layer of the entire horizontal plane along the edge of the foundation.
1.2.10. Fastening or strengthening of stone walls that deviate from the vertical position and have deformations.
1.2.11. Relaying dilapidated cornices, parapets, firewalls, pits and protruding parts of walls.
1.2.12. Relaying individual, worn out, window and door lintels.
1.2.13. Insulation of dilapidated wooden walls with striped boards over roofing or with additional sheathing with boards and backfilled with fine slag.
1.2.14. Partial dismantling of existing internal walls and laying of new ones (up to 25% of the total volume), associated with the redevelopment of premises.
1.2.15. Replacement of various types of aggregates in walls with stone, reinforced concrete and metal frames(up to 50% of the total wall area).
1.2.16. Change of dilapidated crowns of log or block walls (up to 20%).
1.2.17. Continuous caulking of log or block walls.
1.2.18. Partial replacement of sheathing, backfilling and slab insulation of frame walls (up to 50% of the total wall area).
1.2.19. Change or repair of sheathing and insulation of wooden plinths.
1.2.20. Repair of stone plinths of wooden walls with their re-laying up to 50% of the total volume.
1.2.21. Setting up again and changing worn clamps of log and block walls.
1.2.22. Strengthening reinforced concrete and stone columns with clips.
1.2.23. Repair and partial replacement (up to 20%) of columns not associated with additional loads from newly installed equipment.

1.3. Partitions.
1.3.1. Repair, change and replacement of worn partitions with more progressive designs.
1.3.2. Partial redevelopment with an increase in the total area of ​​partitions (up to 20%).
1.3.3. Repair of partitions with the replacement of unusable strappings and boards in the amount of more than 2 m2 in one place.
1.3.4. Strengthening the sound insulation of partitions by upholstering them with an additional layer of hardboard, cardboard or other materials, followed by applying a layer of plaster, wallpapering or painting.
1.3.5. Replenishment of the backfill of two-layer partitions, followed by boarding and all finishing work.

1.4. Roofs and roofs.
1.4.1. Replacement of formwork boards in places of grooves and eaves slopes.
1.4.2. Replacement of dilapidated roof structures with a roof made of prefabricated reinforced concrete elements coated with roofing felt, roofing material and other roofing materials.
1.4.3. Full or partial replacement of dilapidated metal and reinforced concrete trusses.
1.4.4. Reinforcement of trusses when replacing types of coatings (wood-based panels with precast concrete, cold coating with warm coating, etc.), as well as with corrosion of nodes and other elements of metal and prefabricated reinforced concrete trusses.
1.4.5. Partial or complete replacement of rafters, mauerlats and battens under the roof.
1.4.6. Repair or replacement of worn-out metal railings on roofs.
1.4.7. Repair or replacement of worn outdoor fire escapes.
1.4.8. Installation of new manholes on the roof, dormer windows and transitional bridges to them.
1.4.9. Relocation of chimney and ventilation pipes on the roof.
1.4.10. Continuous replacement of dilapidated wall gutters, slopes and covers around chimneys and other protruding devices above the roof.
1.4.11. Reconstruction of light lanterns with low illumination of premises to a large one.
1.4.12. Repair and painting of the supporting structures of skylights.
1.4.13. Repair of mechanical and manual opening and closing devices of skylight bindings.
1.4.14. Partial or complete replacement of dilapidated coating elements, as well as replacing them with more progressive and durable ones.
1.4.15. Partial (more than 10%) or complete change or replacement of the roof (all types).
1.4.16. Reconstruction of roofs in connection with the replacement of roofing materials.
1.4.17. Repair of coatings around chimneys and ventilation pipes, firewalls, parapets and other protruding parts on the roof.
1.4.18. Strengthening of parapets, steel gratings of the fence, repair of ventilation shaft heads, gas ducts, sewer risers and other protruding parts on the roof.
1.4.19. Restoration and repair of stepladders for the safe cleaning of chimneys on roofs with soft coatings or slopes with a steep slope.
1.4.20. Maintenance of outdoor fire escapes for climbing to the roof.

1.5. Interfloor ceilings and floors.
1.5.1. Repair or replacement of interfloor and attic floors.
1.5.2. Replacing individual floor beams, building up the ends of the beams with prostheses with all subsequent work. Replacing the selection between the beams.
1.5.3. Replacing individual structures or ceilings as a whole with more progressive and durable structures.
1.5.4. Strengthening of all elements of interfloor and attic floors.
1.5.5. Gunning of reinforced concrete floors in case of their damage.
1.5.6. Partial (more than 10%) or continuous change of floors (of all types) and their bases.
1.5.7. Reconstruction of floors during repairs with replacement with stronger and more durable ones, while the type of floors must comply with the requirements of norms and specifications for new construction.
1.5.8. Restoration of the concrete base under the floors with the installation of a new floor.
1.5.9. Re-laying clean plank floors with leveling the lag and adding new material.
1.5.10. Re-laying of parquet floors with correction or replacement of lathing.
1.5.11. Re-laying of floors on logs in the ground floors with correction or replacement of the base and restoration of brick columns.
1.5.12. Repair or replacement of underground canal walls.

1.6. Windows, doors and gates.
1.6.1. Complete replacement of dilapidated window and door blocks, as well as gates.

1.7. Stairs and porches.
1.7.1. Partial or complete change of landings, ramps and porches.
1.7.2. Change or strengthening of all types of stairs and their individual elements.
1.7.3. Replacement or repair of railings and handrails of stairs over 5% of their total number.
1.7.4. Installation of new porches.
1.7.5. Change of metal stringers or welding of damaged parts of stringers.

1.8. Internal plastering, facing and painting works.
1.8.1. Renewal of plastering of all premises and repair of plastering in the amount of more than 10% of the total plastered surface.
1.8.2. Upholstery of walls and ceilings with dry plaster.
1.8.3. Restoration or replacement of wall surface cladding in the amount of more than 10% of the total area of ​​cladding surfaces.
1.8.4. Renewal of stucco details indoors.
1.8.5. Painting of window casings, doors, ceilings, walls and floors after the overhaul of these structures.
1.8.6. Oil painting of radiators, heating pipes, water supply, sewerage, gasification after a major overhaul of the system or its new installation, if the costs are incurred at the expense of capital repairs.
1.8.7. Continuous anti-corrosion painting of metal structures.

1.9. facades.
1.9.1. Repair and renewal of cladding with an area of ​​more than 10% of the cladded surface of building facades with the replacement of individual tiles with new ones or plastering of these places with subsequent painting to match the color of the facing slabs.
1.9.2. Full or partial (more than 10%) renewal of the plaster.
1.9.3. Restoration or alteration of rods, cornices, belts, sandriks and other protruding parts of building facades.
1.9.4. Continuous replacement and installation of new drainpipes, as well as all external metal and cement coatings on the protruding parts of building facades.
1.9.5. Restoration of molding and stucco decorations and details.
1.9.6. Continuous painting of building facades with stable compositions.
1.9.7. Change or installation of new gratings and fences on the roofs and balconies of buildings.
1.9.8. Cleaning of facades and plinths with sandblasters.
1.9.9. Change or strengthening of all load-bearing and enclosing structures of balconies and bay windows.
1.9.10. Change of coverings of protruding parts of the building.
1.9.11. Restoration of old or installation of new gates.
1.9.12. Oil painting of facades of wooden buildings.

1.10. Furnaces and hearths.
1.10.1. Repair, alteration and installation of new stoves, kitchen hearths, cast-in boilers and chimneys for them.
1.10.2. Complete refurbishment or installation of new heating stoves, chimneys, ventilation ducts and chimneys and their foundations.
1.10.3. Re-equipment of heating stoves from wood to gas heating or heating with solid fuel.

1.11. Central heating.
1.11.1. The device of central heating instead of the stove with the adaptation of the existing room for a boiler room and the installation of a boiler room. In some cases, if it is impossible to adapt the existing premises for the boiler house, it is allowed to carry out an extension to the existing building of the premises with a built-up area of ​​\u200b\u200bno more than 65 m2 or build a new boiler house building.
1.11.2. Change of individual sections and assemblies of heating boilers, boilers, boiler units or complete replacement of boiler units (if they are not independent inventory objects).
1.11.3. Replacement of the existing central heating pipeline.
1.11.4. Repair and replacement of expanders, steam traps and other network equipment.
1.11.5. The device of remote furnaces and devices for boilers under the blast furnace.
1.11.6. Change and installation of additional sections of heating devices and individual sections of the pipeline.
1.11.7. Repair, re-laying or re-installation of foundations for boilers and other equipment.
1.11.8. Boiler room automation.
1.11.9. Replacing the insulation of pipelines that have become unusable.
1.11.10. Refurbishment of the lining of the boiler and chimneys.
1.11.11. Putting patches on a steel boiler, boiler, steamer, tank.
1.11.12. Manufacture and installation of a new casing.
1.11.13. Restoration or installation of a new lining and lining of central heating boilers.
1.11.14. Replacement of worn-out metal chimneys from boiler rooms.
1.11.15. Change of heating registers.
1.11.16. Connection of buildings to heating networks (with a distance from the building to the network of no more than 100 m).

1.12. Ventilation.
1.12.1. Installation of a new, restoration or reconstruction of the ventilation system.
1.12.2. Partial or complete replacement of air ducts.
1.12.3. Changing fans.
1.12.4. Rewinding or changing electric motors.
1.12.5. Change of gates, deflectors, throttle valves, blinds.
1.12.6. Partial or complete replacement of ventilation ducts.
1.12.7. Change of heaters.
1.12.8. Change of heating units.
1.12.9. Changing filters.
1.12.10. change of cyclones.
1.12.11. Change of individual designs of ventilation chambers.

1.13. Plumbing and sewerage.
1.13.1. Restoration or installation of a new internal water supply and sewerage of the building, pipelines, including water supply and sewerage inlets and their connection to the water supply and sewerage networks. The length of the line from the nearest water inlet or sewer outlet to the street network should not exceed 100 m.
1.13.2. Installation of new water intakes indoors.
1.13.3. Installation of additional manholes on existing yard lines or street networks at the points of connection.
1.13.4. Laying of underground lines of water and sewer pipes.
1.13.5. Replacing the cast-iron cisterns of the latrines with flush taps with alteration of the piping and shortening of the flush pipe.
1.13.6. Replacement of taps, valves and sanitary appliances.
1.13.7. Water tower device.
1.13.8. Installation of new sanitary facilities.

1.14. Hot water supply.
1.14.1. Change and installation of a new hot water supply.
1.14.2. Change of individual sections of the hot water pipeline.
1.14.3. Replacement of worn-out tanks, water heaters and water heaters.
1.14.4. Repair of tanks, coils and boilers, associated with complete disassembly and replacement of individual components and parts.
1.14.5. Change of the pipeline, parts and, in general, pumping units, tanks and pipeline insulation.
1.14.6. Change and installation of baths, showers and fittings for them (shower nets with pipelines, taps, flexible hoses).

1.15. Electrical lighting, communications and power wiring.
1.15.1. Installation of new electric lighting in residential and public buildings and connection to the power supply network.
1.15.2. Replacement of worn-out lighting wiring with a change of installation fittings (switches, knife switches, plugs, cartridges, sockets), and in the event of a major overhaul of the building - the installation of new wiring.
1.15.3. Installation of new and replacement of group distribution and safety boxes and shields.
1.15.4. Reconstruction of electrical wiring with the installation of additional fittings in connection with the redevelopment of the premises.
1.15.5. Automation of electric lighting in the stairwells of buildings.
1.15.6. Replacement of metering devices and protection devices for electrical installations.
1.15.7. Repair or restoration of cable channels.
1.15.8. Replacement of lamps for other types (conventional for fluorescent, etc.).

1.16. Gas supply.
1.16.1. Installation of additional gas equipment in apartments with its connection to the gas network.
1.16.2. Gasification of individual apartments.
1.16.3. Change of individual sections of the gas pipeline.
1.16.4. Replacement of equipment that has become unusable (gas stoves, water heaters) with new equipment.

1.17. Elevators and lifts.
1.17.1. Re-installation of elevators with all types of construction and installation works.
1.17.2. Full or partial replacement of electrical equipment and cargo elevator winches.
1.17.3. Strengthening, full or partial change of metal structures and fencing nets of the mine.
1.17.4. Complete or partial change of electrical wiring in mines.
1.17.5. Dismantling and installation of elevator equipment in connection with work to reduce noise in premises with a permanent presence of people.
1.17.6. Elevator automation.

2. Structures

2.1. Water supply and sewerage facilities. Pipelines and network fittings.
2.1.1. Partial or complete replacement of the anti-corrosion insulation of the pipeline.
2.1.2. Change of individual sections of the pipeline without changing the diameter of the pipes. At the same time, it is allowed to replace cast-iron pipes with steel pipes, ceramic pipes with concrete or reinforced concrete pipes and vice versa, but it is not allowed to replace asbestos-cement pipes with metal pipes (except in emergency cases).
The length of network sections where a continuous change of pipes is allowed should not exceed 200 m per 1 km of the network.
2.1.3. Change of worn fittings, valves, fire hydrants, air vents, valves, standpipes or their repair with the replacement of worn parts.
2.1.4. Change of individual siphon pipes.

2.2. Water supply and sewer networks. Wells.
2.2.1. Repair of masonry wells.
2.2.2. Changing hatches.
2.2.3. Stuffing again trays to replace the destroyed ones.
2.2.4. Replacing worn-out wooden wells.
2.2.5. Restoration of plaster.

2.3. Water supply and sewer networks. Treatment facilities.
2.3.1. Repair or replacement (totally) waterproofing.
2.3.2. Repair and renewal of plaster and ironing.
2.3.3. Relaying brick walls and partitions (up to 20% of the total volume of masonry in the structure).
2.3.4. Sealing leaks in reinforced concrete, concrete and stone walls and bottoms of structures with concrete dismantling in separate places and concreting again.
2.3.5. Continuous shotcrete of the walls of structures.
2.3.6. Repair of drainage around structures.
2.3.7. Replacement of hatches of tanks.
2.3.8. Grating replacement.
2.3.9. Replacement of loading of filters, biofilters, aerofilters.
2.3.10. Replacement of pipelines and fittings.
2.3.11. Change of filter plates.
2.3.12. Relaying the drainage system of silt pads.

2.4. Heat supply. channels and cameras.
2.4.1. Partial or complete change of coatings of channels and chambers.
2.4.2. Partial or complete change of waterproofing of channels and chambers.
2.4.3. Partial re-laying of the walls of brick channels and chambers (up to 20% of the total surface of the walls).
2.4.4. Partial relocation of drainage systems.
2.4.5. Repair of the bottoms of channels and chambers.
2.4.6. Renewal of the protective layer in reinforced concrete structures of channels and chambers.
2.4.7. Changing hatches.

2.5. Heat supply. Pipelines and fittings.
2.5.1. Partial or complete change of thermal insulation of the pipeline.
2.5.2. Renewal of pipeline waterproofing.
2.5.3. Change of individual sections of the pipeline without increasing the diameter of the pipes.
2.5.4. Change of fittings, valves, compensators or their repair with the replacement of worn parts.
2.5.5. Replacement of movable and fixed supports.

2.6. Car roads. Ground cloth.
2.6.1. Treatment of subgrade in places of landslides, landslides, erosion and abysses.
2.6.2. Restoration of drainage and drainage devices.
2.6.3. Restoration of protective and fortifying structures of the subgrade.
2.6.4. Change of individual structures of artificial structures or their replacement with other structures, as well as a complete change of pipes and small bridges (if they are not independent inventory objects, but are part of the subgrade or road as a single inventory object).

2.7. Car roads. Road clothes.
2.7.1. Alignment and replacement of individual cement-concrete slabs.
2.7.2. Laying a leveling layer of asphalt concrete on a cement-concrete surface.
2.7.3. Installation of asphalt concrete pavement on roads with cement-concrete pavement.
2.7.4. Change of cement-concrete pavement to a new one.
2.7.5. Strengthening of asphalt concrete pavement.
2.7.6. Reconstruction of crushed stone and gravel coverings.
2.7.7. Bridge relocation.
2.7.8. Profiling of dirt roads.

2.8. Warehouse and other sites.
2.8.1. Repair and restoration of drainage structures (trays, ditches, etc.).
2.8.2. Relocation of cobblestone areas.
2.8.3. Reconstruction of crushed stone and gravel coverings of sites.
2.8.4. Repair of concrete platforms with laying of a leveling layer of concrete.
2.8.5. Leveling and replacement of individual cement-concrete pads.
2.8.6. Covering sites with asphalt concrete.

2.9. Electrical networks and communications.
2.9.1. Change or replacement of fittings.
2.9.2. Replacing hooks with traverses.
2.9.3. Wire change.
2.9.4. Repair and change of end and connecting cable boxes.
2.9.5. Repair or replacement of grounding devices.
2.9.6. Change of supports (up to 30% per 1 km).
2.9.7. Installation of cable wells.

2.10. Other buildings.
2.10.1. Repair, change or replacement with other supports of racks for air laying of pipelines.
2.10.2. Repair and replacement of platforms, stairs and railings for overhead pipelines.
2.10.3. Repair or change of individual columns (up to 20%) of crane racks.
2.10.4. Repair or replacement of crane beams of crane racks.
2.10.5. Repair of galleries and fuel supply racks of boiler and gas generating substations with a change (up to 20%) of structures without changing foundations.
2.10.6. Change or complete replacement of wooden fence posts.
2.10.7. Repair or change of individual concrete and reinforced concrete pillars (up to 20%) of fences.
2.10.8. Repair of individual sections of fencing elements (up to 40% filling between posts).
2.10.9. Repair of separate sections of solid stone fences (up to 20%).
2.10.10. Repair of individual sections of solid adobe fences (up to 40%).
2.10.11. Repair of chimneys with the change or replacement of the lining, with the installation of hoops, with the restoration of the protective layer of reinforced concrete pipes.
2.10.12. Repair and replacement of individual sections of metal chimneys.
2.16.13. Repair of ash and slag dischargers with complete replacement of individual sections of pipelines (without increasing the diameter).
2.12.14. Repair of loading platforms with a complete change of wooden flooring, blind area or asphalt. Change of individual supports or sections of retaining walls (up to 20%). If the unloading area is part of a storage facility (ramp), a complete change or replacement of all structures is allowed.

The list of works on the overhaul of apartment buildings to be included in the scope of works financed from the funds provided for by Federal Law N 185-FZ; Table 2.3 ( "Methodological recommendations for the formation of the scope of works for the overhaul of apartment buildings financed from the funds provided for by the Federal Law of July 21, 2007 N 185-FZ "On the Fund for Assistance to the Reform of the Housing and Communal Services" (approved by the State Corporation "Fund for Assistance to the Reform of Housing and Communal Services" 15.02.2013)

This list is formed on the basis of the updated lists of work on major repairs recommended by the above normative documents within the framework of the types of work on the overhaul of apartment buildings, defined by Article 15 of the Federal Law N 185-FZ. It is assumed, however, that the provisions of these guidelines apply to apartment buildings subject to major repairs without stopping their operation. As a result of the overhaul, all necessary work must be performed to bring the common property of an apartment building into a technically sound condition by restoring or replacing all parts of structures and engineering systems that have a shorter service life between regular (according to the standard service life) overhauls than bearing structures.

2.3.2. Consistent and methodical linking of technological processes to the list of works given in Table 2.3 of these recommendations is contained in Section 3.

Table 2.3

Name of types of work in accordance with Part 3 of Article 15 of Federal Law N 185-FZ

Subspecies and list of works

Repair of intra-house engineering systems of electricity, heat, gas, water supply, sanitation

1. Repair or replacement of engineering systems:

1.1. Cold water supply, including:

1.1.1. Repair or replacement of water meter units;

1.1.2. Repair or replacement of distributing highways and risers;

1.1.3. Replacement of shut-off valves, including those on a branch from the risers to the apartment;

1.1.4. Repair or replacement in the complex of equipment of booster pumping units

1.1.5. Repair or replacement of equipment, pipelines and fire water supply equipment

1.2. Repair or replacement of the hot water system, including:

1.2.1. Repair or replacement of TRZH, heat exchangers, boilers, pumping units and other equipment (as part of the common property) in the complex for the preparation and supply of hot water to the distribution network;

1.2.2. Repair or replacement of distributing highways and risers;

1.2.3. Replacement of shut-off valves, including those on a branch from the risers to the apartment.

1.3. Repair or replacement of the sewerage and drainage system, including:

1.3.1. Repair or replacement of outlets, prefabricated pipelines, risers and hoods;

1.3.2. Replacing valves, if any;

1.4. Repair or replacement of the heating system, including;

1.4.1. Repair or replacement of distributing highways and risers;

1.4.2. Replacement of shut-off and control valves, including those on a branch from risers to heating appliances in residential premises;

1.4.3. Regrouping or replacement of heating devices in common areas and replacement of heating devices in residential premises that do not have disconnecting devices;

1.4.4. Installation, repair or replacement in the complex of ITP equipment (individual heating points) and in the presence of booster pumping units

1.5. Repair or replacement of the gas supply system, including:

1.5.1. Repair or replacement of intra-house distributing highways and risers;

1.5.2. Replacement of shut-off and control valves, including those on a branch from risers to household gas appliances in residential premises;

1.6. Repair or replacement of the power supply system, including:

1.6.1. Repair or replacement of main switchboard (main switchboard), distribution and group boards;

1.6.2. Repair or replacement of intra-house distributing highways and risers of communal and apartment lighting;

1.6.3. Replacement of branches from floor shields or boxes of apartment meters and installation and lighting fixtures for public lighting;

1.6.4. Replacement of electrical networks to power the electrical equipment of elevators and electrical equipment to ensure the operation of engineering systems;

2. Modernization of engineering systems, including:

2.1. Mandatory use of modernized heating devices and pipelines made of plastic, metal-plastic, etc. and a ban on the installation of steel pipes

2.2. Transfer of the existing power supply network to increased voltage;

2.3. Replacement of lighting fixtures for public lighting needs with energy-saving ones;

2.4. Re-equipment of heating points and water metering units;

3. Replacing stove heating with central heating

with device

boiler houses,

heat pipelines and

thermal points;

roof and other autonomous sources of heat supply

4. Equipment systems

cold and

hot water supply,

sewer,

gas supply

with accession

to existing backbone networks with a distance from the input to the point of connection to the mains up to 150 m,

device

gas ducts,

water pump,

boiler rooms.

Repair or replacement of elevator equipment recognized as unsuitable for operation, if necessary, repair of elevator shafts

Repair and replacement of elevator equipment with its modernization, including:

1. Repair or complete replacement of elevator equipment, recognized as unsuitable for operation;

2. Repair, if necessary, mines, replacement of side mines;

3. Repair of machine rooms;

4. Repair, replacement of automation elements and scheduling of elevator equipment;

5. Equipment of devices necessary for connection to existing systems automation and dispatching of elevator equipment

Roof repair

1. Repair of roof structures:

1.1. From wooden structures:

1.1.1. Repair: with partial replacement

rafter legs,

Mauerlatov

Lathing solid and discharged from bars

1.1.2. Antiseptic and fireproofing of wooden structures.

1.1.3. Insulation of the under-roof (attic) floor

1.1.4. Repair (replacement of dormers)

1.2. From reinforced concrete rafters and roofing decks:

1.2.1. Troubleshooting reinforced concrete rafters and roofing decks;

1.2.2. Insulation of the under-roof (attic) floor

1.2.3. Roofing screed repair;

2. Replacement of roof coverings

2.1. Complete replacement of the metal coating of roofs with junctions;

2.2. Complete replacement of the roof covering from rolled bituminous materials (roofing material) for roofs from built-up materials with adjoining device

2.3. Complete replacement of the roof covering from piece materials (slate, tiles, etc.) with adjoining device

3. Repair or replacement of the drainage system (overhangs, gutters, grooves, trays) with the replacement of drainpipes and products (external and internal);

4. Repair or replacement of roofing elements

4.1. Roof hole repair

4.2. Repair of air vents, repair or replacement of dormer windows and other devices for ventilation of the attic space;

4.3. Change of caps on the heads of smoke ventilation blocks and ventilation shafts;

4.4. Change of openings of parapets, firewalls, superstructures

4.5. Repair (plastering, painting) and insulation of smoke ventilation units and elevator shafts

4.6. Restoration or replacement of the fence on the attic roof;

5. Reconstruction of non-ventilated combined roofs to ventilated ones with insulation of the under-roof (attic) floor

Repair of basements belonging to common property in apartment buildings

1. Repair of sections of basement walls and floors

2. Insulation of walls and basement ceilings of basements

3. Waterproofing the walls and floor of the basement

4. Repair technical premises with the installation of metal doors.

5. Repair of air ducts, basement windows, pits and external doors

6. Sealing the passages of inputs and outputs of engineering networks in the outer walls (performed during the repair of networks)

7. Repair of the blind area

8. Repair or replacement of the drainage system

Warming and repair of facades

1. Repair of facades that do not require insulation

1.1. Repair of plaster (texture layer), including architectural order;

1.2. Repair of facing tiles;

1.3. Painting on plaster or on a textured layer;

1.4. Repair and restoration of sealing of horizontal and vertical joints of wall panels of large-block and large-panel buildings;

1.5. Repair and restoration from the side of the facade of the sealing of the joints of window and door openings of common areas;

1.6. Painting from the side of the facade of window frames;

1.7. Repair of enclosing walls;

1.8. Repair and replacement of windows and balcony doors (as part of common property);

1.9. Repair or replacement of exterior doors.

2. Work on the repair of facades requiring insulation

2.1. Repair and insulation of enclosing walls with subsequent surface finishing

2.2. Repair of windows and balcony doors (as part of the common property) or replacement with energy-saving design windows and doors (window blocks with triple glazing, etc.) with their subsequent insulation (sealing)

2.3. Repair of entrance external doors with their subsequent insulation or replacement with metal doors in an energy-saving design

3. Work common to both groups of buildings

3.1. Repair of balconies with replacement of consoles if necessary, waterproofing and sealing with subsequent painting

3.2. Reinforcement of canopy structures above entrances and last floors with subsequent surface finishing

3.3. Strengthening the structures of cornice blocks with subsequent surface finishing

3.4. Changing window sills

3.5. Change of drainpipes

3.6. Basement repair and insulation

Installation of collective (common house) metering devices for resource consumption and control units (thermal energy, hot and cold water, electric energy, gas)

Installation of collective (common house) consumption meters:

Thermal energy for the needs of heating and hot water supply;

cold water consumption,

electrical energy,

Resource management nodes, with equipment for automation and dispatching devices to provide remote accounting and control;

Repair of the foundations of apartment buildings.

1. Repair or replacement of foundations.

1.1. Sealing and jointing of joints, seams, cracks in foundation elements. Protective layer device.

1.2. Elimination of local defects and deformations by strengthening the foundation.

Notes:

1. During the overhaul of structures and engineering systems as part of the common property of an apartment building, as determined by Federal Law 185-FZ, at least 50% of each structure and engineering system is replaced.

2. In-house heating systems as part of common property include: risers, heating elements in common areas, in residential premises - branches from risers to the first disconnecting device (if it is not available, to the point of interface with a heater, heating element), regulating and stop valves; collective (common house) heat energy meters, as well as other equipment located on these networks.

3. In the event that during the performance of work on the overhaul of structures and engineering systems as part of the common property of MD, due to the technological and design features of the repaired (replaced) structures and engineering systems, it is necessary to dismantle or destroy parts of the property that is not part of the common property of MD , work on its restoration is carried out at the expense of capital repairs, which should be provided for in the design and estimate documentation.

4. In the event that a heating system with a hidden laying of pipelines, which is not repairable (Appendix 2), is designed in an apartment building, it is allowed to re-install a heating system with open laying of pipelines and heating appliances, heating elements, including in residential premises.

Loading...Loading...